The schedules listed here reflect what is established in statute, rules, or Orders.
However, PUCs and utilities sometimes deviate from these schedules.
Please check the most recent proceeding by going to the "Important Recurring Proceedings" section for each utility below.
Policy AreaDemand-Side Management Annual Energy Efficiency and Peak Load Reduction Report
ScheduleThe utility must submit a demand-side management report to the Commission every year by May 1.
Policy AreaRenewable Energy Goals
ScheduleAn electric corporation shall develop and maintain a plan for implementing the renewable energy certificate program. Progress reports shall be filed with the Commission by January 1 of the years 2010, 2015, 2020 and 2024.
Policy AreaIntegrated Resource Plan
ScheduleThe utility shall submit its integrated resource plan (IRP) every two years for a 20-year planning horizon. The IRP will also include an action planning for a 4-year planning horizon.