Policy AreaIntegrated Resource Plan
ScheduleBy April 1, every two years (each even year) load-serving entities must file 15 year plans. Every odd year utilities must file work plans that outline the 15-year resource plan. A third report, due the following year, sets forth the load-serving entity’s method for assessing potential resources, the sources of its current assumptions, and a general outline of the procedures it will follow for public input.
Policy AreaElectric Energy Efficiency Rules
ScheduleUtilities file implementation plans by June 1 every other year (odd years), and submit a progress report on DSM programs by March 1 each year.